As 2024 comes to a close we can look back upon a busy and successful year for Infraland in what has been a turbulent energy market! Of our 21 solar PV sites under development, we have seen planning consents come through for a number of projects including:
60 MWp at Oakley near Loughborough
10 MWp with 8 MW battery storage at Burton Top near Harrogate
15 MWp at New Milton in Hampshire
22 MWp at Rowley Hill near Haverhill in Essex
A further 40MWp at Wickham Hall near Bishop Stortford
We were also successful in obtaining Contract for Difference (CfD) contracts for our projects at Chestnut Farm (23 MWp), Highfields Farm, Costock (66 MWp) and Burton Top which were our first entries into the scheme.
Our Chestnut Farm project started construction in September following successful project financing with Novuna and Ethical Power acting as EPC contractor. Hall Farm is also under construction after an investment by Ampyr Solar Europe.
Our team is very proud to be moving forward with these projects in collaboration with investors, and we look forward to more progress in 2025.